Pakistan Saves $27 Million in Cross-Border Hydroelectric Power Project

By Prof. Engr. Zamir Ahmed Awan 2 min read

Wire desk byline Sourced from Xinhua, Dawn, Arab News, Anadolu and Minute Mirror. Translated and abridged by the GSRRA Desk.

Pakistan Saves $27 Million in Cross-Border Hydroelectric Power Project
  • Pakistan has achieved significant financial savings of over $27 million in the Central Asia-South Asia Electricity Transmission and Trade Project (CASA-1000) project after successfully negotiating down contractor claims related to care and custody costs.

The Engineering, Procurement, and Construction (EPC) contractor, a joint venture of Hitachi Energy and Cobra Instalaciones y Servicios, had initially raised its care and custody claims to approximately USD 32.9 million for Pakistan and USD 28.5 million for Tajikistan.

A high-level meeting held on March 9–10, 2026, in Ludvika, Sweden, led to the successful outcome. The Pakistani delegation included Additional Secretary of the Ministry of Energy (Power Division), Syed Imtiaz Hussain Shah, and Managing Director of National Grid Company, Altaf Hussain.

Following negotiations, the parties agreed to cap the total care and custody cost at USD 9 million for both Pakistan and Tajikistan combined, covering the period up to February 2028. This decision is expected to save Pakistan more than USD 27 million while ensuring the continued maintenance and operational readiness of critical high-voltage direct current (HVDC) assets during the interim phase.

The agreement also allows for a limited extension of up to three months beyond February 2028, if required, subject to a 5% monthly escalation in costs.

The CASA-1000 project, which aims to enable electricity trade between Central and South Asia, has faced delays due to geopolitical instability in Afghanistan. As a result, commissioning of the HVDC system is now expected by September 2027, necessitating interim care and custody arrangements to preserve infrastructure readiness.

Reference Link:- https://propakistani.pk/2026/03/20/pakistan-saves-27-million-in-cross-border-hydroelectric-power-project/

Prof. Engr. Zamir Ahmed Awan
Prof. Engr. Zamir Ahmed Awan Founder & Chair, Global Silk Route Research Alliance

Zamir Ahmed Awan is the founder and Chair of the Global Silk Route Research Alliance, a think tank in Islamabad. He studied engineering at Shanghai University in the 1980s, and years later he went back to China as Pakistan's science counsellor in Beijing, from 2010 until 2016, working on science and higher education cooperation between the two countries.…

All articles by this author

Leave a Reply

Your email address will not be published. Required fields are marked *

Memberships & Partners · 伙伴联盟