Pakistan: 300MW Balakot Hydropower project: Nepra initiates tariff determination

作者 Prof. Engr. Zamir Ahmed Awan 2 分钟阅读

新闻台署名 来源:新华社、《黎明报》、《阿拉伯新闻》、阿纳多卢通讯社与《分钟镜报》。由 GSRRA 编辑部翻译并节选。

Pakistan: 300MW Balakot Hydropower project: Nepra initiates tariff determination

National Electric Power Regulatory Authority (NEPRA) has admitted a tariff petition filed by the Pakhtunkhwa Energy Development Organization (PEDO) for the 300MW Balakot Hydropower Project and scheduled a public hearing on July 2, 2026.

According to a public notice issued by the regulator, the project is proposed to be established in Balakot, district Mansehra, Khyber Pakhtunkhwa. The installed capacity of the project is 300 megawatts, with auxiliary consumption estimated at 2 percent and a plant factor of 43.5 percent.

PEDO has sought a levelised tariff of Rs 17.7103 per kilowatt-hour (kWh) for a control period of 30 years, equivalent to approximately 6.3576 US cents per kWh.

READ ALSO: PEDO opposes exclusion of two hydropower projects from IGCEP

The total estimated cost of the project has been projected at USD 612.56 million. Of this, USD 513.22 million has been allocated for engineering, procurement and construction (EPC), while USD 22.10 million covers PEDO overheads, management costs and administrative charges. An amount of USD 57.09 million has been earmarked for land acquisition, resettlement, security and legal charges, whereas soft costs are estimated at USD 20.15 million.

NEPRA will conduct a public hearing on the petition on July 2, 2026, at 2:00 pm at its headquarters in Islamabad.

The hearing will also be accessible via an online platform.

The Authority has invited all interested and affected parties to participate in the proceedings. Stakeholders may file intervention requests within seven days of the publication of the notice, in accordance with NEPRA’s Tariff Standards and Procedure Rules, 1998.

The regulator noted that comments from stakeholders would also be considered in the final determination of the tariff.

The Balakot Hydropower Project is part of Khyber Pakhtunkhwa’s broader strategy to harness its hydropower potential and contribute to the national grid with low-cost renewable energy.

Reference Link:- https://www.brecorder.com/news/40426896/300mw-balakot-hydropower-project-nepra-initiates-tariff-determination

Prof. Engr. Zamir Ahmed Awan
Prof. Engr. Zamir Ahmed Awan 全球丝绸之路研究联盟创始人兼主席

Zamir Ahmed Awan is the founder and Chair of the Global Silk Route Research Alliance, a think tank in Islamabad. He studied engineering at Shanghai University in the 1980s, and years later he went back to China as Pakistan's science counsellor in Beijing, from 2010 until 2016, working on science and higher education cooperation between the two countries.…

该作者的全部文章

Leave a Reply

Your email address will not be published. Required fields are marked *

成员与合作伙伴 · 伙伴联盟